How big is the solar system installed at Pinder Brothers?
Alliant Energy installed a 19.7kW solar PV system using 48 panels paired with a Solis inverter. The installation took 3 days from arrival on site to commissioning.

Pewter & Silverware Manufacturing
Funding ApprovedEstablished 1877. 19.68kW flat-roof system with ballast mounts.
Established in 1877, Pinder Brothers are a family business who manufacture fine pewter and silverware. A 19.68kW system with 48 panels and a Solis inverter was laid on an east/west split flat roof using a flat roof mounting kit with ballast.
Like most pewter & silverware manufacturing operations, Pinder Brothers faced a structural exposure to wholesale electricity prices — a cost line that doubled for many UK businesses between 2021 and 2023 and shows no sign of returning to pre-crisis levels. With significant daytime load and suitable roof space, on-site generation was the obvious lever, but the project needed to stand on its own commercial merits: predictable payback, manufacturer-backed warranties, and zero operational disruption during install.
Following a structural roof survey and DNO capacity check, Alliant Energy specified a 19.7kW array using 48 high-efficiency mono-PERC panels, paired with a Solis hybrid inverter. The Solis platform was chosen for its export-management capability and remote firmware updates, allowing the array to be tuned over its life without site visits. Surplus generation is exported to the grid under a Smart Export Guarantee tariff, providing a secondary revenue stream alongside the primary saving on imported electricity.
The full installation completed in 3 days, scheduled around the customer's operating hours to avoid downtime. Work was carried out by Alliant Energy's directly employed Experienced engineers — no subcontracted labour. The system was commissioned to G99 requirements, registered with the Microgeneration Certification Scheme, and handed over with monitoring access, electrical certification, and structural sign-off documents on the day of completion.
In its first full year of operation the system is on track to save Pinder Brothers approximately £3,700 on electricity costs, with a payback term of 5 Years and a projected total ROI of 863%. Over the 25-year warranted life of the panels, the cumulative saving is forecast at £200,000 — a figure that improves materially if grid prices continue their long-term upward trend, and that benefits from the UK's 100% full-expensing capital allowance for qualifying solar assets.
The installation displaces roughly 4.8 Tonnes of CO₂ emissions every year compared with grid-sourced electricity. Over the system's 25-year design life that is the equivalent of removing more than Pinder Brothers's entire annual Scope 2 footprint several times over — a material data point for ESG, B-Corp and net-zero reporting frameworks.
Pewter & Silverware Manufacturing businesses typically run daytime electrical loads — refrigeration, machinery, IT, lighting, compressors — that overlap closely with solar generation. That overlap is what drives strong economics: every unit generated and consumed on-site replaces a unit that would otherwise be bought from the grid at full commercial rates. The Pinder Brothers project demonstrates how the model scales for this kind of operation.
Alliant Energy installed a 19.7kW solar PV system using 48 panels paired with a Solis inverter. The installation took 3 days from arrival on site to commissioning.
Pinder Brothers saves approximately £3,700 per year on electricity, with projected lifetime savings of £200,000 over the system's 25-year guaranteed performance period. The payback term is 5 Years, delivering a total ROI of 863%.
Yes — this project was delivered with funding support (grant or asset finance). Alliant Energy helps eligible UK businesses access capital allowances under full expensing, asset-finance facilities, and Power Purchase Agreements (PPAs) so solar can be installed with little or no upfront cost.
The system avoids around 4.8 Tonnes of CO₂ emissions every year compared with grid-sourced electricity. Over a 25-year design life that's a material contribution toward Scope 2 reduction and any ESG or net-zero reporting commitments the business holds.
Probably — the same hardware platform (panels, hybrid inverter, optional battery) scales from roughly 10kW up to 1MW+. The deciding factors are roof area, daytime electricity use, current unit rate, and grid-connection capacity. Alliant Energy carries out a free desktop feasibility study and follow-up site survey before quoting.
Three ways to get started
Get a tailored quote in one working day. No obligation. No hard sell. Speak to a renewable energy engineer — not a salesperson — at a time that suits you.
Quality you can trust
We pride ourselves on delivering high-quality renewable energy solutions. Our experienced installers ensure every system is fitted to the highest standards, backed by a 25-year performance warranty and fully insured installations for total peace of mind.